Original Industrial Spare Part

GE DS200RTBAG2A Retrofit-Compatible RTB for Legacy Systems

Verify the part, confirm the platform family, and move straight into quotation with the right commercial details.

SKU: DS200RTBAG2A PLC & Industrial Automation Modules GE

RFQ Ready

Pricing by RFQ

How Buyers Usually Use This Page

  • Confirm the exact part number and platform family before sending the quote request.
  • Use direct email when quantity, condition, and destination are already defined internally.
  • Switch to the broader brand or category archive when you need alternates nearby.

Series Navigation

Move through the most common platform families behind this part.

GE DS200RTBAG2A Retrofit-Compatible Relay Terminal Board for Legacy Systems

The GE DS200RTBAG2A is a Relay Terminal Board (RTB) designed for use within the GE Mark VI Turbine Control System platform. As a critical interface component between the control logic and field wiring, the DS200RTBAG2A provides reliable relay output termination for discrete control signals in gas turbine, steam turbine, and combined-cycle power generation applications. With a growing number of Mark V and Mark VI installations reaching end-of-life or requiring partial modernization, the DS200RTBAG2A has become one of the most sought-after retrofit and replacement components for engineers managing legacy turbine control infrastructure.

NINERMAS maintains verified in-stock inventory of the DS200RTBAG2A, with each unit subjected to functional testing prior to shipment and backed by a 12-month warranty. Whether you are replacing a failed board, building a spare parts buffer, or executing a phased control system upgrade, this component is available for immediate dispatch to minimize your plant downtime.

Upgrade Compatibility Table

Parameter Details
Part Number DS200RTBAG2A
Manufacturer GE (General Electric)
Series Mark VI Turbine Control System (DS200 Series)
Component Type Relay Terminal Board (RTB)
Primary Function Relay output termination for discrete field signals
Compatible Platforms GE Mark V, Mark VI, Mark VIe (with adapter verification)
Interface / Backplane DS200 Series backplane connector — verify slot assignment before installation
Wiring Compatibility Terminal block wiring; confirm existing field cable gauge and labeling
Installation Space Standard Mark VI control cabinet panel mount — confirm physical clearance
Communication Link Hardwired relay outputs; no fieldbus protocol dependency
Replacement Scope Direct replacement for failed or degraded DS200RTBAG2A units
Pre-Shipment Testing Full functional test performed on every unit
Warranty 12 Months from date of shipment
Country of Origin United States
Condition Refurbished / Surplus New (as available)
Lead Time In stock — ships within 1–3 business days

Retrofit Planning for Existing Automation Systems

Replacing the DS200RTBAG2A within an operating Mark VI turbine control cabinet requires careful pre-work to avoid introducing new faults during the changeover. Before removing the existing board, engineers should document all terminal wiring connections using the plant’s as-built drawings, cross-referencing against the GE Mark VI wiring diagram for the specific turbine unit. Field cables connected to the relay terminal board carry discrete output signals — including trip relays, alarm outputs, and permissive contacts — so any mislabeling or transposition during reconnection can result in incorrect turbine behavior during restart.

The DS200RTBAG2A interfaces with the Mark VI I/O controller through the DS200 Series backplane. When planning the retrofit, confirm that the replacement board’s revision level (G2A) is compatible with the firmware version running on the associated DS200IOCAG1A I/O Controller Board. In some installations, the I/O controller and terminal board revisions must be matched to avoid address mapping conflicts. If the site is running an older Mark V controller migrating toward Mark VI architecture, additional interface adapters or a DS200TCQAG1A Quad-Core Processor Board upgrade may be required to bridge the communication gap between legacy and modern I/O structures.

Power supply integrity is another critical checkpoint. The Mark VI cabinet typically distributes 28VDC and 125VDC through dedicated power distribution boards such as the DS200VPBLG1A Power Distribution Board. Before installing the DS200RTBAG2A, verify that the relay coil voltage supply rail is within specification and that no upstream fuse or breaker has been tripped by the fault that caused the original board failure. Installing a new relay terminal board into a cabinet with an unresolved power fault will result in immediate re-failure.

For sites where the Mark VI system communicates with a plant DCS or SCADA platform via Ethernet Global Data (EGD) or Modbus TCP, the relay output states mapped through the DS200RTBAG2A will need to be verified in the HMI tag database after replacement. Operators using a GE Cimplicity HMI or third-party SCADA should confirm that all relay status points are reading correctly before returning the turbine to automatic control. This is particularly important for trip relay outputs, where a latched or inverted signal could prevent a safe turbine start.

In multi-turbine installations, it is common practice to maintain a local spare parts inventory that includes not only the DS200RTBAG2A but also companion components such as the DS200SDCCG3A Speed and Dynamics Controller, DS200TBCBG1A Terminal Board, and DS200EXPSG1A Expansion Board. Having these boards on-site reduces the mean time to repair (MTTR) when a control system fault occurs during peak generation periods. NINERMAS can supply these components individually or as part of a coordinated spare parts package, with each item tested and documented before shipment.

For plants executing a broader Mark V to Mark VI migration, the DS200RTBAG2A replacement is often one step in a multi-phase upgrade that also involves replacing the DS200DSPXG1A Digital Signal Processor Board, reconfiguring the DS200TCDAG1A Analog I/O Terminal Board, and updating the turbine control application software. NINERMAS technical support can assist with compatibility verification across the full DS200 Series component set to ensure a coherent upgrade path.

Downtime Control During System Migration

Minimizing turbine downtime during a DS200RTBAG2A replacement requires a structured approach that begins well before the maintenance window opens. The first priority is to obtain a verified replacement unit — not a speculative order — so that the board is physically on-site and tested before the turbine is taken offline. NINERMAS ships pre-tested units with a functional test report, allowing the maintenance team to confirm the board’s condition before the outage begins.

During the outage, the recommended sequence is: isolate the turbine from the grid, de-energize the Mark VI cabinet following the plant’s lockout/tagout (LOTO) procedure, photograph all terminal wiring on the DS200RTBAG2A before disconnection, remove the faulty board, install the replacement, reconnect all field wiring in sequence, and perform a continuity check before re-energizing. The entire process, when well-prepared, can typically be completed within a two-to-four hour maintenance window for an experienced controls technician.

After re-energization, the Mark VI system should be allowed to complete its self-diagnostic cycle before any turbine start attempt. Monitor the GE Toolbox diagnostic software for any I/O fault alarms referencing the relay output points associated with the DS200RTBAG2A. If the system reports a board communication fault, verify that the backplane connector is fully seated and that the board address jumpers (if applicable to the revision) are set correctly for the slot position.

For critical baseload or peaking units where even a four-hour outage carries significant financial impact, NINERMAS recommends maintaining a site-level hot spare of the DS200RTBAG2A. Given the board’s role in relay output termination — including trip and alarm functions — an unplanned failure without a spare on-site can extend an outage from hours to days while waiting for a replacement to be sourced and shipped. With NINERMAS’s in-stock inventory and expedited shipping capability, next-day delivery is available for most destinations, but having a local spare eliminates this risk entirely.

Retrofit Support FAQ

Q1: Is the DS200RTBAG2A a direct drop-in replacement for all Mark VI relay terminal board positions?
The DS200RTBAG2A is designed for specific relay output termination slots within the Mark VI cabinet. While it is a direct replacement for a failed DS200RTBAG2A, it is not interchangeable with other terminal board types such as the DS200TCDAG1A (analog I/O) or DS200TBCBG1A (general terminal board). Always verify the part number on the failed board before ordering a replacement.

Q2: What testing is performed before shipment, and what documentation is provided?
Every DS200RTBAG2A shipped by NINERMAS undergoes a functional test that verifies relay coil operation, contact continuity, and backplane connector integrity. A test report is included with each shipment. The unit is also inspected for physical damage, corrosion, and component condition. All units are covered by a 12-month warranty from the date of shipment.

Q3: Can the DS200RTBAG2A be used in a Mark V system, or is it Mark VI-specific?
The DS200RTBAG2A is primarily designed for the Mark VI platform. While some DS200 Series components have cross-compatibility with Mark V installations, the relay terminal board’s backplane interface and wiring configuration should be verified against the specific Mark V cabinet drawings before installation. NINERMAS technical support can assist with compatibility verification for your specific application.

Q4: What is the long-term supply outlook for the DS200RTBAG2A, and can NINERMAS support ongoing procurement?
The DS200RTBAG2A is a discontinued OEM part, but NINERMAS maintains a managed inventory of surplus and refurbished units sourced from verified supply channels. We support long-term procurement agreements for power generation operators who require a guaranteed supply of Mark VI spare parts over a multi-year maintenance horizon. Contact our team to discuss volume pricing and reserved inventory arrangements.

Product Series

Mark VI

Country of Origin

US

Catalog Continuation

Nearby part numbers around DS200RTB.

Use this lane when the buyer is comparing adjacent model numbers, revision-near items, or closely related spare variants within the same brand family.

Open this lane

Catalog Continuation

More GE modules in the catalog.

Use the brand lane to compare nearby part numbers, platform-adjacent modules, and other inquiry-ready listings before sending your final RFQ.

Open this lane

Catalog Continuation

Alternative parts within PLC & Industrial Automation Modules.

Stay inside the same system family when you need substitutes, adjacent modules, or a broader shortlist for procurement review.

Open this lane

Industrial RFQ Support

Need a fast quote for a specific part number or system family?

Send your inquiry with brand, series, quantity, condition, and destination details. We will follow up on availability, lead time, and shipping options.

CallPhone MailEmail WAChat TopBack